Adams Residence "Mat House"

Construction Timeline

1939
"But finally the day came, and with a storm forecasted, we started moving up here on Saturday, September 20. Bob was in school, so Billie and I had to carry our belongings and tear down the shack, then use that lumber again to board in living quarters at the house. After making a gillion trips -then helping pull nails on the side, by night I was so tired I didn't know my name. All day Billie would say, ‘It's sure going to rain like the dickens before we get moved’. But with all the threatening clouds, it didn't rain then. So Sunday we finished boarding in, and with Bob's help, by sun-down we were again housed in".
Bea Adams, September 22, 1939
The family of three moved into a section of the incomplete house. The area that was boarded in for their "winter quarters" was approximately 8’x 26’, and their walls were tarpaper and the siding from the tent/shack.
10/1939Kitchen sink installed; cold water only
12/1939Redwood siding deliverd - put up inside first
12/23/1939Celloglass, shower drain and pipe purchased;
pepper trees have been planted
  
1940
02/14/1940Electricity installed
02/1940Brick floor started
05/01/1940Plumbing installation OK'd after changes;
some outside siding installed
06/02/19401 sliding celloglass door installed, not very successful
06/21/1940Shower fixtures and toilet flush-box installed
07/03/1940Shower completed, but no hot water
07/06/1940Power saw purchased
08/02/194010 celloglass doors installed; all tarpaper removed
08/10/1940Butane tank purchased for gas stove
11/10/1940Fireplace started
11/25/1940First hot water heater
  
1941
01/10/1941Carport and hot water heater shed completed
03/10/1941Some kitchen cabinets in
08/08/1941Rear shed framing up
  
1942
01/12/1942Gas heaters converted to burn butane, in use
12/13/1942Ceiling up in Bob's bedroom
  
1943
10/14/1943Mr. Wright ordering tule mat for roof
Bill Adams all set up for building screen doors.
12/1943Glass doors and screens installed
  
1944
01/1944Tule mat not delivered; cedar shakes used
03/1944Glass delivered for windows
08/1944Brick floors "terrazzo ground" - not dry enough to wax and seal until 1/45

 Previous Page

First Page

Top of Page

 
 
Add A Listing Site Map Name Index Privacy Policy Disclaimer Contact Us



This page best viewed at a minimum of 1038 x 768 resolution using the Firefox, Chrome, or Safari browsers.

Things to Do in Los Angeles, California
SEO by Adeso Technologies
© 2010 The Okay Network